Amberwood at Holland is expected to receive its Temporary Occupation Permit (TOP) in the 2nd quarter of 2029, subject to authority approval, with expected vacant possession on 30 June 2030 and expected legal completion on 30 June 2033. Each of these dates also marks a stage in the progressive payment scheme, so the timeline shapes both when a household moves in and when each payment falls due.
This post sets out the full Amberwood at Holland timeline, from the Government Land Sales award to legal completion, explains what each milestone means for a buyer, and shows how payments follow construction.
| Milestone | Date |
|---|---|
| Government Land Sales tender closed | 29 July 2025 |
| Site awarded to Sim Lian Land and Sim Lian Development | 7 August 2025 |
| 99-year lease begins | 4 November 2025 |
| Preview opened | 11 September 2026 |
| Sales bookings opened | 26 September 2026 |
| Expected TOP | 2nd quarter 2029 (subject to authority approval) |
| Expected vacant possession | 30 June 2030 |
| Expected legal completion | 30 June 2033 |
Dates from Sim Lian and the Government Land Sales public record.
The latest milestones and announcements are posted on the Amberwood at Holland latest updates page.
The Holland Link site was the first Government Land Sales site released in the new Holland Plain precinct. After the tender closed on 29 July 2025, it was awarded on 7 August 2025 to Sim Lian Land Pte Ltd and Sim Lian Development Pte Ltd, which develop Amberwood at Holland through Sim Lian JV (Holland) Pte. Ltd. The 99-year lease runs from 4 November 2025.
The preview opened on 11 September 2026 and sales bookings opened on 26 September 2026. The main contractor is Sim Lian Construction Co. (Pte) Ltd, as the group builds its own projects, a practice rooted in its beginnings as Sim Lian Construction in 1976. Recent Sim Lian completions include Treasure at Tampines, with 2,203 units, in 2023 and The Botany at Dairy Farm in 2026. The Amberwood at Holland developer page covers the full Sim Lian track record.
TOP is the permit that allows the completed homes to be occupied. At Amberwood at Holland it is expected in the 2nd quarter of 2029, subject to authority approval. For buyers, TOP triggers the 25% payment stage, and for upgrading couples it also starts the six-month window for selling a first home to claim the ABSD refund, as at October 2026.
Vacant possession is the handover of the home to the buyer, when keys are collected and the household can begin renovation and move in. The expected date at Amberwood at Holland is 30 June 2030.
Legal completion is the final stage of the purchase, when the last 15% of the price is paid. The expected date is 30 June 2033.
Amberwood at Holland is sold under the progressive payment scheme for homes bought before completion, so each instalment is linked to a construction stage rather than paid in full upfront:
| Stage | Payment |
|---|---|
| Option to Purchase (booking fee, in cash) | 5% |
| Sale and Purchase Agreement, within 8 weeks | 15% |
| Completion of foundation | 10% |
| Reinforced concrete framework | 10% |
| Partition walls | 5% |
| Roofing | 5% |
| Doors, windows, electrical and plumbing | 5% |
| Car park, roads and drains | 5% |
| TOP | 25% |
| Legal completion | 15% |
Progressive Payment Scheme for uncompleted residential property, as at October 2026.
CPF savings and bank loans can be used from the Sale and Purchase Agreement stage onwards,. The Amberwood at Holland payment scheme page explains each stage, the Amberwood at Holland progressive payment calculator estimates the amount due at each milestone, and the post on the Amberwood at Holland payment scheme covers the schedule in depth.
The surroundings of Amberwood at Holland continue to develop alongside the project. Holland Link and Holland Plain roads are to be re-aligned by LTA, scheduled by 2030 and subject to LTA. The future Community Plain, a new park planned beside the development, will link towards the Rail Corridor, and a wetland park is also planned in Holland Plain.
King Albert Park station on the Downtown Line is minutes from the development and will become an interchange with the Cross Island Line when CRL Phase 2 opens, targeted for 2032 by LTA. A future pedestrian link through the Community Plain is planned to connect to the CRL station. The King Albert Park MRT interchange guide covers these rail plans in detail.
To see the homes that will be handed over from 2030, book an Amberwood at Holland showflat viewing, or ask the Amberwood at Holland Sales Concierge for the price list and available units.

How to book an Amberwood at Holland showflat viewing at Prince Charles Crescent, the three showflat layouts on display and what to bring to a booking.

Who can buy at Amberwood at Holland: ABSD rates for citizens, PRs, foreigners and companies, couple reliefs and MAS loan limits, as at October 2026

All 16 unit types at Amberwood at Holland, from 872 to 1,572 sq ft, with the 3-, 4- and 5-bedroom mix, Luxe Collection homes and layout features.
The Sales Concierge sends the e-brochure, the full set of sixteen floor plans and the current price list for Amberwood at Holland, and arranges a private viewing of the three show units at the sales gallery at a time that suits you.

No obligation. The Sales Concierge responds personally to every enquiry.
To talk it through instead, call +65 6200 6220 or send a WhatsApp message to the same number.